Western Hospital Project

Client Brief

Electric Results completed a $3M, 3 stage project in a little under 2 years starting in July 2019 and with handover of the final stage in March 2021.

This project was at Western Hospital. Electric Results performed, in house, the Electrical Services contract, the Mechanical Electrical Contract and the BMS services contract which included the following:

ER2260
ER03887

Stage 1 – Theatre 3 and surrounds

  • Demolition of the existing doctor’s lunchroom and supporting areas
  • Addition of extra space in the building footprint to allow for the building of a new orthopaedic theatre including sterile stock stores and a new decontamination area.
  • Provision of DALI lighting and AS/NZS3003:2018 compliant electrical fit out of the theatre to body protected status using isolation transformers and LIOM’s as the method of protection.
  • Provision of the building management system for the stage to include control and monitoring of:
    • Temperature and humidity
    • Number of air changes per hour
    • Room pressure
  • This was across the theatre and the supporting rooms
  • Provision of new switchboards, UPS, Security, structured cabling and nurse call systems

Stage 2 – Major Infrastructure upgrade

Electrical-Maintenance
ER2247

Stage 3 – Theatre 4 hybrid cardiac theatre

  • Demolition of the existing grange ward, Endoscopy suite and CSSD
  • Building of a new
    • holding bay
    • recovery ward
    • procedure room
    • Cardiac Theatre
    • CSSD
    • Sterile Stock Store
    • Supporting rooms
    • Building of a temporary CSSD so that theatres could continue to operate during the building of the new one
  • Provision of DALI lighting and AS/NZS3003:2018 compliant electrical fit out of the theatre to body protected status using isolation transformers and LIOM’s as the method of protection.
  • Provision of the building management system for the stage to include control and monitoring of:
    • Temperature and humidity
    • Number of air changes per hour
    • Room pressure
  • This was across the theatre and the supporting rooms
  • Provision of 3 new switchboards, UPS, Security, structured cabling and nurse call systems

Commissioning and handover of the entire three stages with high honours from the consulting engineers from both Mechanical and Electrical Disciplines.

Electric Results were awarded both the Master Electricians state and national commercial project of the year for this project.

The consulting Engineers are happy to provide a reference for Electric Results for this project.

  • Lucid
  • Gary Clifford – Associate and discipline leader of the Electrical Services team
  • Tim Randall – Senior Mechanical Engineer

Contact details can be provided on request.